Service Restore on 2026-09-23 18:00 p.m.

發布日期:2026-09-23
開始日期:2026-09-23 18:00
結束日期:2026-09-23 18:00
在此公告停機維護已經完成,我們的服務已於2026-09-23 18:00 PM回復正常。

[維護資訊]

開始時間:2026-09-19 18:00 PM

結束時間:2026-09-23 18:00 PM

[維護報告]
配合變電站高壓盤維護作業,機房需完全斷電。DiCOS Apps 及 Slurm 提交的工作若在2026-09-19 18:00尚未完成,我們將會停止並刪除您已提交的工作。

有任何問題,歡迎來信至 dicos-support@twgrid.org。

Best Regards,
DiCOS Support Team
----------------------------------------------------------------------------------------------------------

We would like to inform you that our maintenance is complete and service is restored.

[Maintenance Information]

Start Time:2026-09-19 18:00 PM

End Time:2026-09-23 18:00 PM

Maintenance Summary: Due to high-voltage switchgear for maintenance, the data center will require a complete power shutdown. Any DiCOS Apps and Slurm jobs that remain unfinished by 18:00 on Sep 19, 2026 will be terminated and removed.

For more information, contact the IT Service Desk by emailing dicos-support@twgrid.org.

Best Regards,
DiCOS Support Team